Buildings and Facilities19PE0072

CONSTRUCTION OF BOKOD MUNICIPAL BUILDING, BOKOD, BENGUET

CONSTRUCTION OF BOKOD MUNICIPAL BUILDING, BOKOD, BENGUET is a DPWH-tracked public work in Benguet 1st DEO, Cordillera Administrative Region. Reported contract value: ₱4,944,714.59. Status: Reported complete (DPWH). Contractor on record: F B BANTALES ENGINEERING CONST. Figures trace to dpwh.

Benguet 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-19-0023090

₱187,580.00 · FY2019

Released to Bago National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

82 projects · ₱3.5B total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF PUERTO PRINCESA WEST COASTAL BYPASS ROAD, BRGY. BACUNGAN-SIMPOCAN, PTO. PRINCESA CITY, PALAWAN

Region IV-B, Region IV-B

2023₱187.8M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS KAMOG JCT. - CALOT - PAPPA - BAGONG - BALLUAY - TUEL JCT. (SECTION 2 OF BLISTT OUTER RING CIRCUMFERENTIAL ROAD) INCL. ROW

Cordillera Administrative Region, Cordillera Administrative Region

2018₱137.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS, AND DECLARED TOURISM DESTINATIONS BALLAY-TABIO-TONOMAN-BULALACAO-TAWANGAN-LUSOD ROAD LEADING TO BULALACAO LAKES AND MT. TABEO, KABAYAN, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2017₱96.5M
Reported complete (DPWH)
No sat.

REHABILITATION/IMPROVEMENT OF MADEGNAK-AGSIMAO ROAD, TINEG, ABRA

Abra DEO, Cordillera Administrative Region

2018₱96.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE -BENGUET-NUEVA VIZCAYA ROAD, K0271+780 - 0271+824, ITOGON, BENGUET, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2018₱96.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MISSING LINKS / NEW ROADS (ROAD OPENING), BESAO - TUBO (VIA TAMBOAN), ABRA

Abra DEO, Cordillera Administrative Region

2018₱96.2M
Reported complete (DPWH)
View all 82 projects →

4. Implementation

Contract Amount

₱4,944,714.59

Progress

Reported complete (DPWH)

Start Date

September 10, 2019

Target End

January 22, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.