Flood Control and Drainage24BG0262

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL, BRGY. SAN MANUEL, NAGUI

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL, BRGY. SAN MANUEL, NAGUI is a DPWH-tracked public work in Isabela 3rd DEO, Region II. Reported contract value: ₱96,489,585.86. Status: Past target date (DPWH On-Going). Contractor on record: MAV CONST SUPPLY AND POWER DEVELOPMENT. Figures trace to dpwh.

Isabela 3rd DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cagayan River Flood Control Project, Barangay San Guillermo ( Phase III ) , Angadanan, Isabela
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0018087

₱-138,030,035.00 · FY2024

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,489,585.86

Progress

Past target date (DPWH On-Going)

Start Date

December 27, 2024

Target End

November 11, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.