Bridges17RA0022

RETROFITTING STRENGTHENING OF MAMBULOC BRIDGE 2 (B00341NR) ALONG PLAZA-CAPITOL ROAD, BRGY 11, BACOLOD CITY

RETROFITTING STRENGTHENING OF MAMBULOC BRIDGE 2 (B00341NR) ALONG PLAZA-CAPITOL ROAD, BRGY 11, BACOLOD CITY is a DPWH-tracked public work in Bacolod City DEO, Negros Island Region. Reported contract value: ₱5,555,289.05. Status: Reported complete (DPWH). Contractor on record: HUMMING BIRD CONST. Figures trace to dpwh.

Bacolod City DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage Structure along Sum-ag River, Brgy. Sum-ag, Bacolod City, Negros Occidental
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0020346

₱409,941.00 · FY2017

Released to Regional Office - IV (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

112 projects · ₱571.4M total · 0 flags

4. Implementation

Contract Amount

₱5,555,289.05

Progress

Reported complete (DPWH)

Start Date

March 1, 2017

Target End

May 14, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.