Construction of Flood Mitigation Structure24JF0008

Construction of Flood Control Structure along Tupilac River (Phase V), RT Lim, Zamboanga Sibugay

Construction of Flood Control Structure along Tupilac River (Phase V), RT Lim, Zamboanga Sibugay is a DPWH-tracked public work in IPIL (CAPITAL) (ZAMBOANGA SIBUGAY), ZAMBOANGA SIBUGAY, Region IX. Reported contract value: ₱57,892,201.40. Status: Reported complete (DPWH). Contractor on record: ST MATTHEW GEN CONTRACTOR & DEVELOPMENT CORP. Figures trace to sumbong.

IPIL (CAPITAL) (ZAMBOANGA SIBUGAY), ZAMBOANGA SIBUGAY, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Sibuguey River, Barangay Lumpanac, Imelda, Zamboanga Sibugay
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-24-0007645

₱1,334,511.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIX-24-0018043

₱1,284,970.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIX-24-0001900

₱946,848.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIX-24-0007646

₱123,222.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

NCA NCA-ROXI-24-0016030

₱6,897,380.00 · FY2024

Released to Davao del Sur District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

61 projects · ₱4.8B total · 15 flags

4. Implementation

Contract Amount

₱57,892,201.40

Progress

Reported complete (DPWH)

Start Date

March 18, 2024

Target End

November 17, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.