Buildings and Facilities24CN0084

CONSTRUCTION OF MULTI-PURPOSE FACILITY, BRGY. LOBOT, DIPACULAO, AURORA

CONSTRUCTION OF MULTI-PURPOSE FACILITY, BRGY. LOBOT, DIPACULAO, AURORA is a DPWH-tracked public work in Aurora DEO, Region III. Reported contract value: ₱19,447,919.20. Status: Past target date (DPWH On-Going). Contractor on record: SO CONST. Figures trace to dpwh.

Aurora DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. Calaocan, Dipaculao, Aurora
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-24-0019554

₱3,782,550.00 · FY2024

Released to Adiong Memorial State College (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,447,919.20

Progress

Past target date (DPWH On-Going)

Start Date

August 23, 2024

Target End

January 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.