Flood Control and Drainage25AA0495

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONST OF FLOOD CONTROL STRUCTURE, BARANGAY 33 CABULALAAN, BACARRA, I.N.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONST OF FLOOD CONTROL STRUCTURE, BARANGAY 33 CABULALAAN, BACARRA, I.N. is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱19,008,889.25. Status: Past target date (DPWH On-Going). Contractor on record: ZEDIK BUILDERS. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay 33 Cabulalaan, Bacarra, Ilocos Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVII-25-0008479

₱38,977,790.00 · FY2025

Released to Ilocos Norte 1st DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

262 projects · ₱2.6B total · 3 flags

4. Implementation

Contract Amount

₱19,008,889.25

Progress

Past target date (DPWH On-Going)

Start Date

April 2, 2025

Target End

September 13, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.