Bridges18CD0228

IMPROVEMENT/REHABILITATION OF LINAWAN BRIDGE AND APPROACHES, DULONG BAYAN, SAN JOSE DEL MONTE CITY, BULACAN

IMPROVEMENT/REHABILITATION OF LINAWAN BRIDGE AND APPROACHES, DULONG BAYAN, SAN JOSE DEL MONTE CITY, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱48,999,648.60. Status: Reported complete (DPWH). Contractor on record: L R TIQUI BUILDERS INC. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures, San Jose River, San Jose Del Monte City, Bulacan
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-18-0034392

₱139,000.00 · FY2018

Released to Zamboanga del Norte 3rd 201 District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

380 projects · ₱29.1B total · 8 flags

Other projects by this contractor

View all 380 projects →

4. Implementation

Contract Amount

₱48,999,648.60

Progress

Reported complete (DPWH)

Start Date

June 7, 2018

Target End

December 3, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.