Bridges21KG0051

BRIDGE PROGRAM-REPLACEMENT OF PERMANENT WEAK BRIDGES DALA MA BRIDGE (FVR) (B01592MN) ALONG BACOLOD-MADALUM HIGHWAY,MUNAI,LANAO DEL NORTE

BRIDGE PROGRAM-REPLACEMENT OF PERMANENT WEAK BRIDGES DALA MA BRIDGE (FVR) (B01592MN) ALONG BACOLOD-MADALUM HIGHWAY,MUNAI,LANAO DEL NORTE is a DPWH-tracked public work in Lanao del Norte 2nd DEO, Region X. Reported contract value: ₱32,273,781.96. Status: Reported complete (DPWH). Contractor on record: AL HUSSEIN CONST. Figures trace to dpwh.

Lanao del Norte 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱36,552,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Facilities along Mandulog River at Brgy. Mandulog, Iligan City, Package 3
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱445,768,000.00 · FY2021

Released to Laguna 3rd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱32,273,781.96

Progress

Reported complete (DPWH)

Start Date

April 12, 2021

Target End

November 24, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.