GAA 2019 OO-119H00006

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROAD WITH SLIP, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, CEBU NORTH HAGNAYA, WHARF RD-K0063+000-K0064+300, K0074+420-

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROAD WITH SLIP, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, CEBU NORTH HAGNAYA, WHARF RD-K0063+000-K0064+300, K0074+420- is a DPWH-tracked public work in Region VII, Region VII. Reported contract value: ₱106,149,077.58. Status: Reported complete (DPWH). Contractor on record: VEN RAY CONST CORP. Figures trace to dpwh.

Region VII, Region VII
Region: Region VII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱106,149,077.58

Progress

Reported complete (DPWH)

Start Date

August 1, 2019

Target End

April 30, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.