Buildings and Facilities17NB0030

CONST. OF MULTI-PURPOSE BLDG., GUADALUPE, ESPERANZA, AGUSAN DEL SUR

CONST. OF MULTI-PURPOSE BLDG., GUADALUPE, ESPERANZA, AGUSAN DEL SUR is a DPWH-tracked public work in Agusan del Sur 1st DEO, Region XIII. Reported contract value: ₱2,884,086.27. Status: Reported complete (DPWH). Contractor on record: ROIM BUILDERS. Figures trace to dpwh.

Agusan del Sur 1st DEO, Region XIII
Region: Region XIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,884,086.27

Progress

Reported complete (DPWH)

Start Date

February 23, 2017

Target End

June 7, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.