Roads23PB0005

ASSET PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-SECONDARY ROADS, ABBUT-CONNER RD- K0543+278-K0543+320

ASSET PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-SECONDARY ROADS, ABBUT-CONNER RD- K0543+278-K0543+320 is a DPWH-tracked public work in Apayao 1st DEO, Cordillera Administrative Region. Reported contract value: ₱3,430,000.00. Status: Reported complete (DPWH). Contractor on record: CAGAYAN PACIFIC STAR CONST CORP. Figures trace to dpwh.

Apayao 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Madduang River Flood Control along Apayao-Abulug River Basin, Sta. 88 + 535 - Sta. 88 + 680 (L/S), Sta. 89 + 133 - Sta. 89 + 633 (R/S), Madduang, Kabugao, Apayao
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-23-0021169

₱646,190.00 · FY2023

Released to Bagamanoc Rural Development High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

10 projects · ₱44.6M total · 0 flags

4. Implementation

Contract Amount

₱3,430,000.00

Progress

Reported complete (DPWH)

Start Date

February 12, 2023

Target End

May 27, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.