Roads21ID0044

ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROAD KILING-TANAUAN-TABONTABON-JULITA RD.-K0932+(-638)-K0932+688,K0934+609-K0935+000,K0936+000 - K0937+000

ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROAD KILING-TANAUAN-TABONTABON-JULITA RD.-K0932+(-638)-K0932+688,K0934+609-K0935+000,K0936+000 - K0937+000 is a DPWH-tracked public work in Leyte 2nd DEO, Region VIII. Reported contract value: ₱10,139,218.34. Status: Reported complete (DPWH). Contractor on record: KAUIE BUILDERS. Figures trace to dpwh.

Leyte 2nd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Anonang River Flood Control, Barangay Anonang, Burauen, Leyte
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱416,067,000.00 · FY2021

Released to Rizal 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱10,139,218.34

Progress

Reported complete (DPWH)

Start Date

July 13, 2021

Target End

September 3, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.