Flood Control and Drainage22CC0170

REHABILITATION OF FLOOD CONTROL STRUCTURE, BAG-BAG CREEK - STA. 00+000 TO STA. 00+376, BRGY. PRITIL, GUIGUINTO, BULACAN

REHABILITATION OF FLOOD CONTROL STRUCTURE, BAG-BAG CREEK - STA. 00+000 TO STA. 00+376, BRGY. PRITIL, GUIGUINTO, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱48,999,998.30. Status: Reported complete (DPWH). Contractor on record: WAWAO BUILDERS. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure, Bag-Bag Creek - Sta. 00+000 to Sta. 00+376, Brgy. Pritil, Guiguinto, Bulacan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0004772

₱32,843,607.00 · FY2022

Released to Regional Office - NCR (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

F

164 projects · ₱9.2B total · 15 flags

4. Implementation

Contract Amount

₱48,999,998.30

Progress

Reported complete (DPWH)

Start Date

April 4, 2022

Target End

January 28, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.