Roads22BG0031

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) - CONSTRUCTION OF ROAD AT BARANGAY YEBAN NORTE-BARANGAY PUNIT, BENITO SOLIVEN, ISA

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) - CONSTRUCTION OF ROAD AT BARANGAY YEBAN NORTE-BARANGAY PUNIT, BENITO SOLIVEN, ISA is a DPWH-tracked public work in Isabela 3rd DEO, Region II. Reported contract value: ₱4,875,267.09. Status: Reported complete (DPWH). Contractor on record: GCPK CONST AND SUPPLY. Figures trace to dpwh.

Isabela 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Pinacanauan River Flood Control Project, Brgy. Yeban-Sur-Maluno Norte, Benito Soliven, Isabela
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-22-0012326

₱-19,851,366.00 · FY2022

Released to Leyte Normal University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

9 projects · ₱56.2M total · 0 flags

Other projects by this contractor

No sat.

CONCRETING OF BRGY. QUINALABASA TO BRGY. MANARING FMR, BRGY. QUINALABASA AND BRGY. MANARING, NAGUILIAN, ISABELA

Isabela 3rd DEO, Region II

2021₱11.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY IV, SAN MATEO, ISABELA

Isabela 3rd DEO, Region II

2024₱9.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY SANTA CRUZ, ALICIA, ISABELA

Isabela 3rd DEO, Region II

2025₱9.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF ROAD, BARANGAY GADDANAN, SAN MATEO, ISABELA

Isabela 3rd DEO, Region II

2025₱5.9M
Past target date (DPWH On-Going)
No sat.

CSSP-CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT)-SINAMAR NORTE VILLA FUERTE AND SAN MARCOS ROADS CONNECTING MUNGGO PRODUCTIO

Isabela 3rd DEO, Region II

2025₱4.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CSSP-CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM ROLL-IT) MARASAT PEQUENO ROAD CONNECTING TO MUNGGO PROCESSING AND PACKAGING CENTER TO

Isabela 3rd DEO, Region II

2025₱4.9M
Reported complete (100% progress, DPWH status On-Going)
View all 9 projects →

4. Implementation

Contract Amount

₱4,875,267.09

Progress

Reported complete (DPWH)

Start Date

February 14, 2022

Target End

May 20, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.