Flood Control and Drainage25OB0270

REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 7)

REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 7) is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱14,038,543.83. Status: Past target date (DPWH On-Going). Contractor on record: RJJC CONST. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure along Barangay 28 (Phase 1), Caloocan City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-25-0011891

₱631,595.00 · FY2025

Released to Regional Office - XI (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,038,543.83

Progress

Past target date (DPWH On-Going)

Start Date

May 20, 2025

Target End

October 16, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.