Flood Control and Drainage21CJ0153

CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS CONSTRUCTION OF ROAD SLOPE PROTECTION ALONG ACCESS ROAD LEADING TO DUEG ECOTOURISM NATURE'S PARK (PHASE 5), SAN CLEMENTE, TARLAC

CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS CONSTRUCTION OF ROAD SLOPE PROTECTION ALONG ACCESS ROAD LEADING TO DUEG ECOTOURISM NATURE'S PARK (PHASE 5), SAN CLEMENTE, TARLAC is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱93,507,932.04. Status: Reported complete (DPWH). Contractor on record: LOUREL DEVELOPMENT CORP FORMERLY :LOUREL D. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱43,516,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures Along Moriones River Right Bank Including Road Component, Balanti Section (Phase V), Sta. 0+000 - Sta. 0+421, Balanti, Tarlac City, Tarlac
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-21-0012869

₱2,518,429.00 · FY2021

Released to Division of Quirino (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

16 projects · ₱1.5B total · 0 flags

4. Implementation

Contract Amount

₱93,507,932.04

Progress

Reported complete (DPWH)

Start Date

November 11, 2021

Target End

June 14, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.