Roads21JB0045

ROAD CONCRETING FROM NATIONAL HIGHWAY TO AT SITIO SILANGIT, BARANGAY PANGALALAN, SINDANGAN, ZAMBOANGA DEL NORTE.

ROAD CONCRETING FROM NATIONAL HIGHWAY TO AT SITIO SILANGIT, BARANGAY PANGALALAN, SINDANGAN, ZAMBOANGA DEL NORTE. is a DPWH-tracked public work in Zamboanga del Norte 2nd DEO, Region IX. Reported contract value: ₱1,910,709.02. Status: Reported complete (DPWH). Contractor on record: JIMWEN CONST. Figures trace to dpwh.

Zamboanga del Norte 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱4,200,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Barangay Kauswagan, Sergio Osmena, Zamboanga del Norte
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱392,621,000.00 · FY2021

Released to Batangas 1st District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

315 projects · ₱2.7B total · 0 flags

4. Implementation

Contract Amount

₱1,910,709.02

Progress

Reported complete (DPWH)

Start Date

August 30, 2022

Target End

September 22, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.