Flood Control and Drainage20IA0069

CONSTRUCTION OF FLOOD CONTROL, SITIO LOMBOY, BRGY. CALUMPANG, NAVAL, BILIRAN

CONSTRUCTION OF FLOOD CONTROL, SITIO LOMBOY, BRGY. CALUMPANG, NAVAL, BILIRAN is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱19,414,720.00. Status: Reported complete (DPWH). Contractor on record: ROVING PREMIER CONTRACTORS INC. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Sitio Lomboy, Brgy. Calumpang, Naval, Biliran
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-20-0005530

₱16,404,321.00 · FY2020

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱19,414,720.00

Progress

Reported complete (DPWH)

Start Date

October 15, 2020

Target End

March 8, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.