Bridges17IF0025

CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROAD - REPLACEMENT OF PERMANENT WEAK BRIDGE, MACATOL BRIDGE (B00211LT) ALONG PALOMPON - ISABEL - MERIDA - ORMOC ROAD

CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROAD - REPLACEMENT OF PERMANENT WEAK BRIDGE, MACATOL BRIDGE (B00211LT) ALONG PALOMPON - ISABEL - MERIDA - ORMOC ROAD is a DPWH-tracked public work in Leyte 4th DEO, Region VIII. Reported contract value: ₱2,936,217.45. Status: Reported complete (DPWH). Contractor on record: GMP BUILDERS. Figures trace to dpwh.

Leyte 4th DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Pagsanga-an Flood Control, Brgy. Lilo-an, Ormoc City, Leyte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-17-0021054

₱487,933.00 · FY2017

Released to 'Amang' Rodriguez Re Medical Center fo (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,936,217.45

Progress

Reported complete (DPWH)

Start Date

February 20, 2017

Target End

May 20, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.