Roads25PM0003

ORGANIZATIONAL OUTCOME 1 - ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - JCT TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD - K0426 + 400 - K0426+580

ORGANIZATIONAL OUTCOME 1 - ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - JCT TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD - K0426 + 400 - K0426+580 is a DPWH-tracked public work in Mountain Province 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱14,694,725.86. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: JFO CONST. Figures trace to dpwh.

Mountain Province 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Buringal Proper, Sta. 065+052 - Sta. 065+240 and Sta. 65+671 - Sta. 65+879, Buringal, Paracelis, Mountain Province
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-25-0016547

₱218,629.00 · FY2025

Released to Davao de Oro State College (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,694,725.86

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 31, 2025

Target End

October 17, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.