Roads18IL0074

FLOOD CONTROL AND DRAINAGE-DRAINAGE/PROTECTION WORKS-LOCAL INFRASTRUCTURE PROGRAM/CONSTRUCTION OF DRAINAGE CANAL, IBARRA, PUROK DIVISORIA TO PUROK BUGNAY, MAASIN CITY, SOUTHERN LEYTE (CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD) MAASIN CITY, SOUTHERN L

FLOOD CONTROL AND DRAINAGE-DRAINAGE/PROTECTION WORKS-LOCAL INFRASTRUCTURE PROGRAM/CONSTRUCTION OF DRAINAGE CANAL, IBARRA, PUROK DIVISORIA TO PUROK BUGNAY, MAASIN CITY, SOUTHERN LEYTE (CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD) MAASIN CITY, SOUTHERN L is a DPWH-tracked public work in Southern Leyte 1st DEO, Region VIII. Reported contract value: ₱1,978,787.59. Status: Reported complete (DPWH). Contractor on record: JQD CONST. Figures trace to dpwh.

Southern Leyte 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bitanhuan Flood Control along Daang Maharlika (S00223LT) Libagon, Southern Leyte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-18-0012182

₱40,000.00 · FY2018

Released to Regional Office - IVA (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

18IL0074 (FLOOD CONTROL AND DRAINAGE-DRAINAGE/PROT

₱1,854,256.00 · JQD CONSTRUCTION & GENERAL SERVICES

Contractor

250 projects · ₱2.7B total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - SOGOD TO BUENAVISTA, BONTOC BYPASS ROAD, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2024₱96.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BYPASS AND DIVERSION ROADS - MAASIN CITY COASTAL BYPASS ROAD (WEST BYPASS ROAD SEGMENT 8), SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2025₱96.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF PANCIL - AURORA - CADARU

Southern Leyte 1st DEO, Region VIII

2025₱96.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - MAASIN CITY COASTAL BYPASS ROAD (WEST BYPASS ROAD SEGMENT 7), SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2024₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMS, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, MAASIN AIRPORT, MAASIN CITY, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2022₱96.4M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - SOGOD TO BUENAVISTA, BONTOC BYPASS ROAD, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2025₱76.3M
Past target date (DPWH On-Going)
View all 250 projects →

4. Implementation

Contract Amount

₱1,978,787.59

Progress

Reported complete (DPWH)

Start Date

March 22, 2018

Target End

September 27, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.