Flood Control and Drainage25C00372

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY CALASAG (DOWNSTREAM), SAN ILDEFONSO, BULACAN

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY CALASAG (DOWNSTREAM), SAN ILDEFONSO, BULACAN is a DPWH-tracked public work in Bulacan 3rd DEO, Region III. Reported contract value: ₱95,061,688.22. Status: Past target date (DPWH On-Going). Contractor on record: JMLD CONST. Figures trace to dpwh.

Bulacan 3rd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Drainage Canal, Barangay Santa Barbara, Baliuag, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-CAR-25-0008445

₱4,870,231.00 · FY2025

Released to Mountain Province State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

113 projects · ₱1.9B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-FLOOD MITIGATION STRUCT. PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONST. OF FLOOD CONTROL STRUCT. ALONG ANYATAM-MAPANIQUE CREEK, PHASE 5, SAN ILDEFON

Region III, Region III

2024₱133.0M
Ongoing (DPWH-reported)
No sat.

CONVERGENCE & SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJ. ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCT. PROTECTING MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF FLOOD CTRL. STRUCTURE ALONG ANYATAM-MAPANIQUE CREEK,PHASE 8,SAN ILDEFONSO,BUL.

Region III, Region III

2024₱114.1M
Ongoing (DPWH-reported)
No sat.

CONVERGE. AND SPECIAL SUPPORT PROG.-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-SIPAG- FLOOD MITIGATION STRUCTS. PRTOTECTING MAJOR/STRAT. PUBLIC BLDGS./FACILITIES-CONST. OF FLOOD MITIGATION STRUCT. ALONG SAN MIGUEL RIVER, SEGMENT B (SIOJO ST. SEC.)

Bulacan 3rd DEO, Region III

2025₱95.1M
Past target date (DPWH On-Going)
No sat.

CONVERG. AND SPL. SUPPORT PROG.-SUST. INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-SIPAG-FLOOD MITIGATION STRUCT. PROTECTING MAJ./STRAT. PUBLIC BLDGS./FACS.-CONST. OF RIVERBANK PROTECTION STRUCT. ALONG MALANGAAN RIVER(DOWNSTREAM), BRGY. CAMACHILE, DONA REMEDIO

Bulacan 3rd DEO, Region III

2025₱95.1M
Past target date (DPWH On-Going)
No sat.

CONVERG. AND SPL. SUPPORT PROG.-SUST. INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-SIPAG-FLOOD MITIGATION STRUCT. PROTECTING MAJ./STRAT. PUBLIC BLDGS./FACS.-CONST. OF RIVERBANK PROTECTION STRUCT. ALONG MALANGAAN RIVER(UPSTREAM), BRGY. CAMACHILE, DONA REMEDIOS

Bulacan 3rd DEO, Region III

2025₱95.1M
Past target date (DPWH On-Going)
No sat.

CONVERGE. AND SPECIAL SUPPORT PROG.-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTS .PROTECTING MAJOR/STRATEGIC PUBLIC BLDGS./ FACILITIES-CONST. OF FLOOD MITIGATION STRUCT. ALONG SAN MIGUEL RIVER, SEG. A (SIOJO ST. SEC.),

Bulacan 3rd DEO, Region III

2025₱95.1M
Past target date (DPWH On-Going)
View all 113 projects →

4. Implementation

Contract Amount

₱95,061,688.22

Progress

Past target date (DPWH On-Going)

Start Date

March 14, 2025

Target End

January 7, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.