Flood Control and Drainage20MD0095

CONSTRUCTION OF LIBUNGAN RIVER FLOOD CONTROL PROJECT (KAPAYAWI SECTION-PHASE II), KAPAYAWI, LIBUNGAN, COTABATO

CONSTRUCTION OF LIBUNGAN RIVER FLOOD CONTROL PROJECT (KAPAYAWI SECTION-PHASE II), KAPAYAWI, LIBUNGAN, COTABATO is a DPWH-tracked public work in Cotabato 1st DEO, Region XII. Reported contract value: ₱29,400,000.00. Status: Reported complete (DPWH). Contractor on record: J-1 BUILDERS CORP FORMERLY: J-ONE BUILDERS. Figures trace to dpwh.

Cotabato 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Libungan River Flood Control Project (Kapayawi Section-Phase II), Kapayawi, Libungan, Cotabato
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXII-20-0000087

₱3,293,000.00 · FY2020

Released to Regional Office - XII (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

160 projects · ₱1.4B total · 0 flags

4. Implementation

Contract Amount

₱29,400,000.00

Progress

Reported complete (DPWH)

Start Date

February 14, 2020

Target End

September 14, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.