Construction of Flood Mitigation Structure21EB0086

Construction of Flood Protection Dike, Barangay Claudio Salgado, Sablayan, Occidental Mindoro

Construction of Flood Protection Dike, Barangay Claudio Salgado, Sablayan, Occidental Mindoro is a DPWH-tracked public work in OCCIDENTAL MINDORO, Region IV-B. Reported contract value: ₱18,802,621.46. Status: Reported complete (DPWH). Contractor on record: JRMX CONST & GEN MERCHANDISE. Figures trace to sumbong.

OCCIDENTAL MINDORO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Protection Dike, Barangay Claudio Salgado, Sablayan, Occidental Mindoro
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007601

₱23,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014213

₱10,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010197

₱26,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-21-0007128

₱561,785.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-21-0007129

₱52,744.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010299

₱4,000,000.00 · FY2021

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱18,802,621.46

Progress

Reported complete (DPWH)

Start Date

March 22, 2021

Target End

February 1, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.