Construction of Flood Mitigation Structure23EE0031

Construction of Labangan Bridge I Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 229.02, Coron, Palawan

Construction of Labangan Bridge I Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 229.02, Coron, Palawan is a DPWH-tracked public work in CORON (PALAWAN), PALAWAN, Region IV-B. Reported contract value: ₱20,088,519.55. Status: Reported complete (DPWH). Contractor on record: JRMX CONST & GEN MERCHANDISE. Figures trace to sumbong.

CORON (PALAWAN), PALAWAN, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱20,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Labangan Bridge I Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 692, Coron, Palawan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Palawan 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱20,088,519.55

Progress

Reported complete (DPWH)

Start Date

May 31, 2023

Target End

February 19, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.