Buildings and Facilities17LC0091

CONSTRUCTION OF MPB (EVACUATION CENTER) BRGY. PALMA GIL, TALAINGOD, DAVAO DEL NORTE

CONSTRUCTION OF MPB (EVACUATION CENTER) BRGY. PALMA GIL, TALAINGOD, DAVAO DEL NORTE is a DPWH-tracked public work in Davao del Norte DEO, Region XI. Reported contract value: ₱1,924,758.80. Status: Reported complete (DPWH). Contractor on record: FIVE MASSIVE INFRA. Figures trace to dpwh.

Davao del Norte DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Ising River Upstream, Davao Del Norte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-17-0025737

₱6,325,000.00 · FY2017

Released to Iwahig Prison an Penal Farm (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

209 projects · ₱1.0B total · 0 flags

4. Implementation

Contract Amount

₱1,924,758.80

Progress

Reported complete (DPWH)

Start Date

July 4, 2017

Target End

October 1, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.