CONSTRUCTION OF JCT. SAYRE HIGHWAY TO JCT. KIBAWE - ARAKAN ROAD (KIBAWE SECTION), PACKAGE 2, BUKIDNON

CONSTRUCTION OF JCT. SAYRE HIGHWAY TO JCT. KIBAWE - ARAKAN ROAD (KIBAWE SECTION), PACKAGE 2, BUKIDNON is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱115,205,737.42. Status: Past target date (DPWH On-Going). Contractor on record: JT GAMOLO CONST INCORPORATION FORMERLY:J T GAMOLO CONST 15759. Figures trace to dpwh.

Region X, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 15759

171 projects · ₱5.9B total · 0 flags

4. Implementation

Contract Amount

₱115,205,737.42

Progress

Past target date (DPWH On-Going)

Start Date

May 26, 2025

Target End

May 5, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.