Flood Control and Drainage25KA0041

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (PACKAGE 2), BARANGAY SAN JOSE, MALAYBALAY CITY, BUKIDNON BRGY. SAN JOSE, MALAYBALAY CITY, BUKIDNON 2ND LD

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (PACKAGE 2), BARANGAY SAN JOSE, MALAYBALAY CITY, BUKIDNON BRGY. SAN JOSE, MALAYBALAY CITY, BUKIDNON 2ND LD is a DPWH-tracked public work in Bukidnon 1st DEO, Region X. Reported contract value: ₱125,450,000.00. Status: Past target date (DPWH On-Going). Contractor on record: JT GAMOLO CONST INCORPORATION FORMERLY:J T GAMOLO CONST. Figures trace to dpwh.

Bukidnon 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Miglamin, Malaybalay City, Bukidnon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bukidnon 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱125,450,000.00

Progress

Past target date (DPWH On-Going)

Start Date

February 10, 2025

Target End

February 9, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.