Roads20BC0198

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES, AND ECONOMIC ZONES-STA. FILOMENA-LANGAY BARANGAY ROAD LEADING TO JCT. AYAGA IN SUPPORT OF AGRIBUSINESS, BANGUIAN, AND STA. FILOMENA, ABULUG, CAGAYAN

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES, AND ECONOMIC ZONES-STA. FILOMENA-LANGAY BARANGAY ROAD LEADING TO JCT. AYAGA IN SUPPORT OF AGRIBUSINESS, BANGUIAN, AND STA. FILOMENA, ABULUG, CAGAYAN is a DPWH-tracked public work in Cagayan 2nd DEO, Region II. Reported contract value: ₱2,450,000.00. Status: Reported complete (DPWH). Contractor on record: PRIME MASTER CONST AND DEV'T CORP. Figures trace to dpwh.

Cagayan 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-20-0004901

₱3,873,039.00 · FY2020

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

40 projects · ₱926.0M total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS : PIDDIG, CARASI (ILOCOS NORTE)-CALANASAN-LANGNAO-KABUGAO ROAD - PACKAGE 2 (CONSTRUCTION OF CONCRETE BRIDGE), APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2025₱141.7M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - CONSTRUCTION OF MISSING LINKS/NEW ROADS - CONSTRUCTION OF CONCRETE BRIDGE - SAN JOSE QUIBAL ROAD (BITAG-PEQUEÑO BR. 1), BAGGAO, CAGAYAN

Cagayan 1st DEO, Region II

2025₱98.3M
Ongoing (DPWH-reported)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - GUISING BR. (B01092LZ) ALONG MAHARLIKA HIGHWAY (CAGAYAN VALLEY RD)

Region II, Region II

2025₱67.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF MISSING LINKS / NEW ROADS ABRA-KALINGA-APAYAO ROAD (BULUAN-BANBAN-PUGUIN-SACPIL- PINUKPOK), PACKAGE 3, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2019₱56.3M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-BRIDGE PROGRAM-CONSTRUCTION OF NEW BRIDGES, CONSTRUCTION OF CONCRETE BRIDGE - TALLANG BRIDGE 1 (PHASE II) ALONG BAYBAYOG-BAGGAO-DALIN-STA. MARGARITA RD, BAGGAO, CAGAYAN

Cagayan 1st DEO, Region II

2024₱48.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS - CONSTRUCTION OF ALANNAY FLOOD CONTROL STRUCTURE ALONG ZINUNDUNGAN RIVER, LAS

Cagayan 2nd DEO, Region II

2025₱48.9M
Past target date (DPWH On-Going)
View all 40 projects →

4. Implementation

Contract Amount

₱2,450,000.00

Progress

Reported complete (DPWH)

Start Date

September 11, 2020

Target End

January 18, 2021

5. Audit