GAA 2025 OO-225BC0023

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS - CONSTRUCTION OF ALANNAY FLOOD CONTROL STRUCTURE ALONG ZINUNDUNGAN RIVER, LAS

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS - CONSTRUCTION OF ALANNAY FLOOD CONTROL STRUCTURE ALONG ZINUNDUNGAN RIVER, LAS is a DPWH-tracked public work in Cagayan 2nd DEO, Region II. Reported contract value: ₱48,935,000.01. Status: Past target date (DPWH On-Going). Contractor on record: PRIME MASTER CONST AND DEV'T CORP 43456. Figures trace to dpwh.

Cagayan 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Alannay Flood Control Structure along Zinundungan River, Lasam, Cagayan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cagayan 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 43456

39 projects · ₱903.1M total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS : PIDDIG, CARASI (ILOCOS NORTE)-CALANASAN-LANGNAO-KABUGAO ROAD - PACKAGE 2 (CONSTRUCTION OF CONCRETE BRIDGE), APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2025₱141.7M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - CONSTRUCTION OF MISSING LINKS/NEW ROADS - CONSTRUCTION OF CONCRETE BRIDGE - SAN JOSE QUIBAL ROAD (BITAG-PEQUEÑO BR. 1), BAGGAO, CAGAYAN

Cagayan 1st DEO, Region II

2025₱98.3M
Ongoing (DPWH-reported)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - GUISING BR. (B01092LZ) ALONG MAHARLIKA HIGHWAY (CAGAYAN VALLEY RD)

Region II, Region II

2025₱67.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF MISSING LINKS / NEW ROADS ABRA-KALINGA-APAYAO ROAD (BULUAN-BANBAN-PUGUIN-SACPIL- PINUKPOK), PACKAGE 3, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2019₱56.3M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-BRIDGE PROGRAM-CONSTRUCTION OF NEW BRIDGES, CONSTRUCTION OF CONCRETE BRIDGE - TALLANG BRIDGE 1 (PHASE II) ALONG BAYBAYOG-BAGGAO-DALIN-STA. MARGARITA RD, BAGGAO, CAGAYAN

Cagayan 1st DEO, Region II

2024₱48.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (NWCGH), BRGY. PINILI, LIBERTAD, ABULUG, CAGAYAN (PACKAGE 4)

Cagayan 2nd DEO, Region II

2025₱48.4M
Past target date (DPWH On-Going)
View all 39 projects →

4. Implementation

Contract Amount

₱48,935,000.01

Progress

Past target date (DPWH On-Going)

Start Date

March 7, 2025

Target End

November 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.