Bridges, Roads20BC0046

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS-ACCESS ROAD ALONG MINANGA NAMUAC ROAD LEADING TO ESTUARY SAND DUNES AND BEACHES, SANCHEZ MIRA, CAGAYAN

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS-ACCESS ROAD ALONG MINANGA NAMUAC ROAD LEADING TO ESTUARY SAND DUNES AND BEACHES, SANCHEZ MIRA, CAGAYAN is a DPWH-tracked public work in Cagayan 2nd DEO, Region II. Reported contract value: ₱14,700,000.00. Status: Reported complete (DPWH). Contractor on record: DANDEX CONST. Figures trace to dpwh.

Cagayan 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Dugo Flood Control Structure along Abulug River, Abulug, Cagayan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-20-0004901

₱3,873,039.00 · FY2020

Released to Masbate National Comprehensive High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

20BC0046-Construction/Improvement of Access Roads

₱10,409,649.89 · DANDEX CONSTRUCTION

Contractor

B

138 projects · ₱1.6B total · 0 flags

4. Implementation

Contract Amount

₱14,700,000.00

Progress

Reported complete (DPWH)

Start Date

March 5, 2020

Target End

January 16, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.