GAA 2016 MFO-116N00006

COMPLETION OF THE EAST - WEST LATERAL ROAD CONNECTING AGUSAN DEL SUR/AGUSAN DEL NORTE TO BUKIDNON, SIMBALAN - DULAG SECTION, INCLUDING BRIDGE (NEW CALAITAN BRIDGE) & APPROACHES, REGION XIII, BUTUAN CITY

COMPLETION OF THE EAST - WEST LATERAL ROAD CONNECTING AGUSAN DEL SUR/AGUSAN DEL NORTE TO BUKIDNON, SIMBALAN - DULAG SECTION, INCLUDING BRIDGE (NEW CALAITAN BRIDGE) & APPROACHES, REGION XIII, BUTUAN CITY is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱131,329,395.13. Status: Reported complete (DPWH). Contractor on record: BBC CONST. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱131,329,395.13

Progress

Reported complete (DPWH)

Start Date

August 31, 2016

Target End

December 8, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.