Roads22PL0008

ORGANIZATIONAL OUTCOME 1: ENSURE SAFETY AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION-PREVENTIVE MAINTENANCE-PRIMARY ROADS - KALINGA-CAGAYAN ROAD (CALANAN-ENRILE SECTION) - K0506+905 - K0507+000, K0512+469 - K0512+931

ORGANIZATIONAL OUTCOME 1: ENSURE SAFETY AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION-PREVENTIVE MAINTENANCE-PRIMARY ROADS - KALINGA-CAGAYAN ROAD (CALANAN-ENRILE SECTION) - K0506+905 - K0507+000, K0512+469 - K0512+931 is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱11,103,709.30. Status: Reported complete (DPWH). Contractor on record: JTM CONST. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Central School/ Sunrise/ Pinuk-Balan, Purok 7/ Hilltop (Cliff) Flood Control, Barangay Dagupan/ Bulanao, Tabuk City, Kalinga
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-22-0005595

₱19,407,042.00 · FY2022

Released to Central Office (NIA) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

114 projects · ₱4.3B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - NAMBARAN-ISABELA RD - K0509 + (-903) - K0520 + 865

Lower Kalinga DEO, Cordillera Administrative Region

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY (CAGAYAN VALLEY RD) - K0490+848 - K0492+1025, K0492+1399.60 - K0494+458, K0499+097 - K0499+216.80

Region II, Region II

2025₱187.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - PEÑABLANCA-CALLAO CAVE ROAD (S05071LZ) - K0475 + 233 - K0483 + 550 & K0484 + 020 - K0486 + 434 (TWO LANES)

Cagayan 3rd DEO, Region II

2025₱144.6M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - KALINGA-CAGAYAN RD (CALANAN-ENRILE SECTION) - K0437 + (-055) - K0441 + 576, K0441 + 600 - K0444 + 214, K0444 + 315 - K0445 + 676

Cagayan 3rd DEO, Region II

2024₱144.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R. A. 11239 - PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG DAANG MAHARLIKA (CAGAYAN VALLEY RD) - K0484+855 - K0486+320, K0487+000 - K0487+484, K0487+610

Region II, Region II

2025₱132.4M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY ( CAGAYAN VALLEY ROAD) - K0471 + 128 - K0472 + 779.20

Region II, Region II

2025₱107.9M
Ongoing (DPWH-reported)
View all 114 projects →

4. Implementation

Contract Amount

₱11,103,709.30

Progress

Reported complete (DPWH)

Start Date

February 15, 2022

Target End

May 10, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.