Buildings and Facilities24AF0090

REHABILITATION OF MULTI PURPOSE BLDG W/ SITE DEVELOPMENT IN BRGY. SAMARA, ARINGAY, LA UNION

REHABILITATION OF MULTI PURPOSE BLDG W/ SITE DEVELOPMENT IN BRGY. SAMARA, ARINGAY, LA UNION is a DPWH-tracked public work in La Union 2nd DEO, Region I. Reported contract value: ₱6,730,369.74. Status: Reported complete (DPWH). Contractor on record: AYANA CONST AND TRADING. Figures trace to dpwh.

La Union 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Aringay River Basin, Brgy. Anduyan, Tubao, La Union
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVI-24-0007260

₱1,000,000.00 · FY2024

Released to La Union 2nd DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱6,730,369.74

Progress

Reported complete (DPWH)

Start Date

March 19, 2024

Target End

July 16, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.