Construction of Flood Mitigation Structure23OE0046

Construction of Retention Basin at Estero dela Reina, (Phase XII), Tondo, Manila City

Construction of Retention Basin at Estero dela Reina, (Phase XII), Tondo, Manila City is a DPWH-tracked public work in CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region. Reported contract value: ₱96,219,232.12. Status: Reported complete (DPWH). Contractor on record: G F FABIAN CONST. Figures trace to sumbong.

CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱40,343,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Mitigation Structure, Easement Road Estero de Pandacan (Tripa de Gallina - P. Quirino Ave.) Manila
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-23-0023041

₱86,456.00 · FY2023

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱96,219,232.12

Progress

Reported complete (DPWH)

Start Date

March 28, 2023

Target End

July 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.