Construction of Flood Mitigation Structure24CD0049

Construction of Flood Control Structure, Sta. 00+208 - Sta. 00+312 (Tawiran-Paliwas Section), Obando, Bulacan

Construction of Flood Control Structure, Sta. 00+208 - Sta. 00+312 (Tawiran-Paliwas Section), Obando, Bulacan is a DPWH-tracked public work in OBANDO (BULACAN), BULACAN, Region III. Reported contract value: ₱144,749,905.80. Status: Reported complete (DPWH). Contractor on record: G F FABIAN CONST. Figures trace to sumbong.

OBANDO (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Guiguinto Flood Control Structure, Pritil Section, Guiguinto, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0006660

₱9,979,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007287

₱1,460,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0000163

₱1,078,312.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007288

₱135,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0016339

₱108,080.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱144,749,905.80

Progress

Reported complete (DPWH)

Start Date

February 22, 2024

Target End

June 28, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.