Buildings and Facilities16DF0166

CONSTRUCTION OF 2 UNITS - 4STY 20CL SHS IN SAN NICOLAS III, BACOOR CITY

CONSTRUCTION OF 2 UNITS - 4STY 20CL SHS IN SAN NICOLAS III, BACOOR CITY is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱66,667,067.51. Status: Reported complete (DPWH). Contractor on record: HEXAMINDZ CORP FORMERLY:KILUSANG MAGKAIBIG. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Canas River, Brgys. Tapia Section, Pinagtipunan, San Juan II Section and Tejero Section, Gen. Trias, Cavite 6th LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-16-0027749

₱8,540,498.00 · FY2016

Released to Division of Sorsogon (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱66,667,067.51

Progress

Reported complete (DPWH)

Start Date

May 31, 2016

Target End

January 10, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.