Roads25BH0028

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, PUROK 4, BARANGAY MINANTE 1, CAUAYAN CITY, ISABELA

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, PUROK 4, BARANGAY MINANTE 1, CAUAYAN CITY, ISABELA is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱5,431,955.65. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: D'LIMITLESS CIVIL ENGINEERING CONST. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. San Fermin, Cauayan City, Isabela
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-25-0017562

₱-1,460,337.00 · FY2025

Released to Rizal Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

31 projects · ₱270.8M total · 0 flags

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (LIBRARY AND YOUTH CENTER), BARANGAY SAN FABIAN, ECHAGUE, ISABELA

Isabela 4th DEO, Region II

2025₱28.8M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - SANTIAGO-TUGUEGARAO RD - K0335 + 066 - K0337 + 415, RAMON, ISABELA

Isabela 3rd DEO, Region II

2025₱22.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY MALIGAYA, CAUAYAN CITY, ISABELA

Isabela 4th DEO, Region II

2024₱19.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - SANTIAGO-TUGUEGARAO RD - K0332 + (-158) - K0334 + 000, RAMON, ISABELA

Isabela 3rd DEO, Region II

2025₱16.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONCRETING OF BURGOS - SAN FRANCISCO FMR, BRGY. BURGOS, ALICIA, ISABELA

Isabela 3rd DEO, Region II

2024₱14.9M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, PAGWADAN AI ROAD, PUROK 5, BRGY. NUNGNUNGAN 1, CAUAYAN CITY,

Isabela 4th DEO, Region II

2025₱14.7M
Past target date (DPWH On-Going)
View all 31 projects →

4. Implementation

Contract Amount

₱5,431,955.65

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 4, 2025

Target End

June 1, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.