Buildings and Facilities19BC0268

LOCAL INFRA PROGRAM-CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. CENTRO 1, CLAVERIA, CAGAYAN

LOCAL INFRA PROGRAM-CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. CENTRO 1, CLAVERIA, CAGAYAN is a DPWH-tracked public work in Cagayan 2nd DEO, Region II. Reported contract value: ₱1,214,916.03. Status: Reported complete (DPWH). Contractor on record: DYLAN EQUIPMENT CONST AND SUPPLIES. Figures trace to dpwh.

Cagayan 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-19-0018277

₱250,056.00 · FY2019

Released to School (Davao del Sur National High School) 0911230 - Digos City National High (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

51 projects · ₱789.3M total · 0 flags

Other projects by this contractor

CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG LAOAG RIVER BASIN, GUISIT RIVER, BRGY. BIMMANGA, PIDDIG, ILOCOS NORTE

Region I, Region I

2023₱82.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MISSING LINKS/NEW ROADS - PIDDIG-CARASI (ILOCOS NORTE) - CALANASAN (APAYAO) CONNECTING CABUGAO-CONNER (APAYAO)-TUAO (CAGAYAN) ROAD, ILOCOS NORTE

Region I, Region I

2022₱72.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG LAOAG RIVER BASIN, GUISIT RIVER, SITIO BALBALATE, BARANGAY ABUCAY, PIDDIG, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2023₱65.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MISSING LINKS/NEW ROADS - PIDDIG-CARASI-CALANASAN ROAD, ILOCOS NORTE

Region I, Region I

2022₱53.1M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM-ROLL-IT)-JCT. MANILA NORTH ROAD TO PINEAPPLE AND S

Cagayan 2nd DEO, Region II

2024₱47.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP) DUPITAC-ESTANCIA ROAD LEADING TO SUNFLOWER FARM AND MAMINMINAW FALLS, PIDDIG, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2023₱31.1M
Past target date (DPWH On-Going)
View all 51 projects →

4. Implementation

Contract Amount

₱1,214,916.03

Progress

Reported complete (DPWH)

Start Date

September 12, 2019

Target End

January 12, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.