CONSTRUCTION OF EVACUATION CENTER, BRGY. LA UNION, PROSPERIDAD, AGUSAN DEL SUR

CONSTRUCTION OF EVACUATION CENTER, BRGY. LA UNION, PROSPERIDAD, AGUSAN DEL SUR is a DPWH-tracked public work in Agusan del Sur 1st DEO, Region XIII. Reported contract value: ₱5,939,986.70. Status: Reported complete (DPWH). Contractor on record: DAVE CONST. Figures trace to dpwh.

Agusan del Sur 1st DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱46,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Maug Flood Control Structure along Riverbank of Maug Bridge Phase III (Downstream), Sta. 0+000.00 - Sta. 0+070.00 R/S, Prosperidad, Agusan del Sur
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXIII-22-0011633

₱147,300,000.00 · FY2022

Released to Division of Butuan City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱5,939,986.70

Progress

Reported complete (DPWH)

Start Date

April 11, 2022

Target End

December 2, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.