Roads24DD0297

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, IMPROVEMENT OF ROAD ALONG ANILAO-KAYUMANG

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, IMPROVEMENT OF ROAD ALONG ANILAO-KAYUMANG is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱18,721,135.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: POWER K CONST SUPPLY. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bawi and Banaba Creek, Padre Garcia, Batangas
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0019178

₱0.00 · FY2024

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

345 projects · ₱6.8B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING FACILITIES, DOH REGION IV-A OFFICE, LIPA CITY

Batangas 4th DEO, Region IV-A

2023₱144.1M
Reported complete (DPWH)
No sat.

LOCALLY-FUNDED PROJECTS, NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES, CONSTRUCTION OF DEPARTMENT OF HEALTH REGION 4A REGIONAL OFFICE MARAWOY, LIPA CITY, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱140.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MISSING LINKS/ NEW ROADS CASILE - TAGAYTAY ROAD, PACKAGE C, LAGUNA

Region IV-A, Region IV-A

2024₱118.1M
Ongoing (DPWH-reported)

CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION/IMPROVEMENT OF TRIBUTARY CREEK AS OUTFALL OF THE DETENTION POND AT BRGY. MAMPLASAN LEADING TO CARMONA-BIÑAN RIVER, BIÑAN CITY, LAGUNA

Region IV-A, Region IV-A

2020₱115.7M
Reported complete (DPWH)
No sat.

SILANGAN ROAD (C.A. YULO AVENUE) CONNECTING SOUTH LUZON EXPRESSWAY LEADING TO THE INDUSTRIAL PARKS, CANLUBANG, CALAMBA CITY, LAGUNA

Region IV-A, Region IV-A

2025₱111.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES & ECONOMIC ZONES SILANGAN ROAD (C.A. YULO AVENUE) CONNECTING SOUTH LUZON EXPRESSWAY LEADING TO THE INDUSTRIAL PARKS, CANLUBANG, CALAMBA CITY, LAGUNA

Region IV-A, Region IV-A

2021₱101.3M
Reported complete (DPWH)
View all 345 projects →

4. Implementation

Contract Amount

₱18,721,135.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 27, 2025

Target End

June 25, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.