Flood Control and Drainage22OB0163

REHABILITATION OF C-6 OPEN CHANNEL, TAGUIG CITY (PHASE 13)

REHABILITATION OF C-6 OPEN CHANNEL, TAGUIG CITY (PHASE 13) is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱89,737,077.67. Status: Reported complete (DPWH). Contractor on record: ALPHA & OMEGA GEN CONTRACTOR & DEVELOPMENT CORP REVOKED 38958. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱18,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Westbank Road, Manggahan Floodway, Pasig City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0004760

₱0.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 38958

57 projects · ₱5.3B total · 0 flags

Other projects by this contractor

View all 57 projects →

4. Implementation

Contract Amount

₱89,737,077.67

Progress

Reported complete (DPWH)

Start Date

February 16, 2022

Target End

October 13, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.