Roads25E00190

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- CONST. OF PUERTO GALERA-ABRA DE ILOG ROAD (MINDORO CIRCUMFERENTIAL ROAD), BRGY. UDALO, ABRA DE ILOG, OCC. MINDORO

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- CONST. OF PUERTO GALERA-ABRA DE ILOG ROAD (MINDORO CIRCUMFERENTIAL ROAD), BRGY. UDALO, ABRA DE ILOG, OCC. MINDORO is a DPWH-tracked public work in Region IV-B, Region IV-B. Reported contract value: ₱186,124,003.72. Status: Past target date (DPWH On-Going). Contractor on record: ALPHA & OMEGA GEN CONTRACTOR & DEVELOPMENT CORP. Figures trace to dpwh.

Region IV-B, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

141 projects · ₱11.1B total · 23 flags

4. Implementation

Contract Amount

₱186,124,003.72

Progress

Past target date (DPWH On-Going)

Start Date

April 6, 2025

Target End

February 6, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.