Flood Control and Drainage25DC0044

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM,CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG TAAL LAKE CIRCUMFERENTIAL

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM,CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG TAAL LAKE CIRCUMFERENTIAL is a DPWH-tracked public work in Batangas 3rd DEO, Region IV-A. Reported contract value: ₱108,199,778.00. Status: Past target date (DPWH On-Going). Contractor on record: GREAT PACIFIC BUILDERS AND GEN CONTRACTOR INC. Figures trace to dpwh.

Batangas 3rd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Mitigation Structure along Pansipit River, Lemery, Batangas (Phase 3)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROI-25-0008577

₱372,885.00 · FY2025

Released to Ilocos Training and Regional Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

296 projects · ₱11.9B total · 3 flags

4. Implementation

Contract Amount

₱108,199,778.00

Progress

Past target date (DPWH On-Going)

Start Date

March 21, 2025

Target End

February 13, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.