Flood Control and Drainage17FB0047

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - REHABILITATION OF FLOOD CONTROL SYSTEM ALONG BAÑAG RIVER, STA. 0+970-STA. 1+245 (L/S) SECTION A MAIN, DARAGA, ALBAY

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - REHABILITATION OF FLOOD CONTROL SYSTEM ALONG BAÑAG RIVER, STA. 0+970-STA. 1+245 (L/S) SECTION A MAIN, DARAGA, ALBAY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱37,640,321.52. Status: Reported complete (DPWH). Contractor on record: SPRING STAR CONST AND SUPPLY. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱38,409,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control System along Bañag River, Sta. 0+435 - Sta. 0+869.80 (R/S) Section A "Main", Sta. 0+689.80 - Sta. 0+756 (B/S) Section A "Main", Daraga, Albay
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-17-0001081

₱650,000.00 · FY2017

Released to San Fabian Nation High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

225 projects · ₱6.8B total · 2 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - BALUD NATIONAL ROAD CONNECTING BARANG

Masbate 2nd DEO, Region V

2023₱135.1M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - C0NSTRUCTION/IMPROVEMENT OF ACCESS OF ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP) - BALUD - PALANI - PANUBIGAN - PAJO -TALISAY ROAD LEADING TO PALANI BEACHES, PANUBIGA

Masbate 2nd DEO, Region V

2023₱115.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - MANDAON - DAYHAGAN ROAD, PACKAGE 1, MASBATE

Masbate 2nd DEO, Region V

2024₱96.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS, MALUBI - CABANGCALAN - DAYHAGAN - TINIGBAN - MATABA ROAD, MASBATE, STA.5+101 - STA.6+245, AROROY, MASBATE

Masbate 2nd DEO, Region V

2022₱96.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS - MANDAON - DAYHAGAN - ROAD, STA.4+350 - STA.5+750, MANDAON, MASBATE

Masbate 2nd DEO, Region V

2022₱96.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS - MALUBI - CABANGCALAN - DAYHAGAN - TINIGBAN - MATABA ROAD, MASBATE, STA. 3+892 - STA. 5+052, NET LENGTH = 2.320 LANE KM (1.160 KM), AROROY, MASBATE

Masbate 2nd DEO, Region V

2021₱96.5M
Reported complete (DPWH)
View all 225 projects →

4. Implementation

Contract Amount

₱37,640,321.52

Progress

Reported complete (DPWH)

Start Date

May 9, 2017

Target End

October 5, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.