Flood Control and Drainage25CJ0218

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SANTA LUCIA RIVER (ANNEX 8), PANIQUI, TARLAC

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SANTA LUCIA RIVER (ANNEX 8), PANIQUI, TARLAC is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱93,413,159.14. Status: Past target date (DPWH On-Going). Contractor on record: 11-16 CONST. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Baka River (Segment 13), Paniqui, Tarlac
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-25-0005277

₱20,000.00 · FY2025

Released to Tarlac DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

244 projects · ₱19.8B total · 8 flags

4. Implementation

Contract Amount

₱93,413,159.14

Progress

Past target date (DPWH On-Going)

Start Date

May 16, 2025

Target End

January 14, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.