Buildings and Facilities16FD0001

CLUSTER PROJECTS: CONST. OF MPB AT A) BRGY. SALVACION, LIBMANAN, CS & B) BRGY. TANAG, LIBMANAN. CS

CLUSTER PROJECTS: CONST. OF MPB AT A) BRGY. SALVACION, LIBMANAN, CS & B) BRGY. TANAG, LIBMANAN. CS is a DPWH-tracked public work in Camarines Sur 2nd DEO, Region V. Reported contract value: ₱3,800,784.75. Status: Reported complete (DPWH). Contractor on record: E GARCIA CONST CORP FOR E GARCIA CONST. Figures trace to dpwh.

Camarines Sur 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Rehabilitation / Improvement of Camaligan Flood Control, Brgy. San Juan - San Ramon, Camaligan, Camarines Sur 3rd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0014680

₱1,739,720.00 · FY2016

Released to Allen National High School (Balicuatro NHS) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

115 projects · ₱7.1B total · 3 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS, ROLANDO A. ANDAYA HIGHWAY, CAMARINES SUR, K0282+(-186)-K0282+(-181), K0282+160-K0282+245, K0282+3

Region V, Region V

2019₱240.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF DAET RIVER FLOOD CONTROL STRUCTURE (DOGONGAN SECTION-PACKAGE

Region V, Region V

2024₱238.7M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF DAET RIVER FLOOD CONTROL STRUCTURE (DOGONGAN SECTION-PACKAGE

Region V, Region V

2024₱236.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, DAET RIVER, BARANGAY BIBIRAO, DAE

Region V, Region V

2025₱235.2M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. SAN JOSE, STA. 000+000-STA. 000+371.65, NAUJAN, OR. MINDORO

Region IV-B, Region IV-B

2025₱231.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. MELGAR A, STA. 000+000-STA. 000+463.95, NAUJAN, OR. MINDORO

Region IV-B, Region IV-B

2025₱230.7M
Past target date (DPWH On-Going)
View all 115 projects →

4. Implementation

Contract Amount

₱3,800,784.75

Progress

Reported complete (DPWH)

Start Date

February 28, 2016

Target End

May 27, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.