Roads17CN0119

RD. UPGRADING (UNPAVED - PAVED) BASED ON GRAVEL RD. STRAT, TRAFFIC BM FOR UPGRADING TO PAVED RD STD(HDM-4) PROJ ANALYSIS, BALER-CASIGURAN RD (DINADIAWAN-CASIGURAN SECT.), K0307+802.61 TO K0308+410.17, K0308+669 TO K0308+709.33, K0319+425.6 TO K0319+798.09

RD. UPGRADING (UNPAVED - PAVED) BASED ON GRAVEL RD. STRAT, TRAFFIC BM FOR UPGRADING TO PAVED RD STD(HDM-4) PROJ ANALYSIS, BALER-CASIGURAN RD (DINADIAWAN-CASIGURAN SECT.), K0307+802.61 TO K0308+410.17, K0308+669 TO K0308+709.33, K0319+425.6 TO K0319+798.09 is a DPWH-tracked public work in Aurora DEO, Region III. Reported contract value: ₱48,451,200.00. Status: Reported complete (DPWH). Contractor on record: ZF CONST. Figures trace to dpwh.

Aurora DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Balitwak Flood Control, San Isidro, San Luis, Aurora
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-17-0006250

₱13,000,000.00 · FY2017

Released to Philippine Sports Commission (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

73 projects · ₱2.8B total · 0 flags

4. Implementation

Contract Amount

₱48,451,200.00

Progress

Reported complete (DPWH)

Start Date

June 27, 2017

Target End

July 2, 2018