Flood Control and Drainage17LA0024

CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG AGUSAN RIVER, BRGY. PANAG, NEW BATAAN, COMPOSTELA VALLEY PROVINCE

CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG AGUSAN RIVER, BRGY. PANAG, NEW BATAAN, COMPOSTELA VALLEY PROVINCE is a DPWH-tracked public work in Davao de Oro 1st DEO, Region XI. Reported contract value: ₱45,862,918.42. Status: Reported complete (DPWH). Contractor on record: AB APONESTO CONST PARTS AND SUPPLY INC. Figures trace to dpwh.

Davao de Oro 1st DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱45,862,918.42

Progress

Reported complete (DPWH)

Start Date

May 30, 2017

Target End

February 11, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.