Flood Control and Drainage25AA0038

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BANBAN RIVER, BARANGAY TAGUIPORO, BANGUI, ILOCOS NORTE

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BANBAN RIVER, BARANGAY TAGUIPORO, BANGUI, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱37,644,248.95. Status: Past target date (DPWH On-Going). Contractor on record: BADOC BUILDERS & SUPPLY INC FORMERLY: BADOC BUILDER & SUPPLY. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Banban River, Barangay Taguiporo, Bangui, Ilocos Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Ilocos Norte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

20 projects · ₱1.1B total · 5 flags

4. Implementation

Contract Amount

₱37,644,248.95

Progress

Past target date (DPWH On-Going)

Start Date

February 17, 2025

Target End

September 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.